Perform a warm shut down on the server. Run:
-
ssh -l root <hostname> shutdown -h now
-
-
-
Disconnect the 10G network interface cable.
-
Pull the 10G network interface cable pull-tab.
-
-
-
Pull the green retention plunger upwards.
-
Pull the server away from the rack, as shown.
-
Pull the server until about (2) inches of the black lid is exposed.
-
-
-
Move the server on the crash cart for transportation or out of rack repairs.
-
-
-
Squeeze (2) lid retention handles towards the center of the node.
-
Slide the lid towards the rear of the server node.
-
Lift and remove the lid.
-
-
-
Use the image to identify the fans.
-
Fans are oriented 0~1, left to right.
-
-
-
Locate the failed fan power connector.
-
System Fan 0 Power Connector
-
System Fan 1 Power Connector
-
Engage the connector by the white header.
-
Disconnect the cable.
-
-
-
Engage the fan on both sides, as shown.
-
Lift the fan from the system.
-
-
-
Align (4) fan rubber grommets (2 as shown), with (4) chassis fan grommet slots.
-
-
-
Secure all (4) fan grommets into their respective slots.
-
-
-
Connect the fan power cable.
-
Make sure to align the key on the connector and header.
-
-
-
Install the lid on the server, as shown.
-
-
-
Slide the server back into the rack.
-
Continue pushing the server until the server chassis pin secures the server.
-
A distinctive 'click' will be felt when the pin secures the server in the rack.
-
-
-
Connect the 10G network interface cable.
-
-
-
Press the power button.
-
This work is licensed under a Creative Commons Attribution 4.0 International License.