  1. Press the button on the server sled release lever and pull the lever. This unlocks the sled from the chassis. This unlocks the sled from the chassis.
    • Press the button on the server sled release lever and pull the lever.

    • This unlocks the sled from the chassis.

  2. Disconnect the 10G SFP+ cable from the network interface controller. Disconnect the SATA / power cables connected to the boot hard disk drive. Node 1 (right-most sled) boot drive is the top drive in the chassis. Node 0 (left-most sled) boot drive is the bottom drive in the chassis.
    • Disconnect the 10G SFP+ cable from the network interface controller.

    • Disconnect the SATA / power cables connected to the boot hard disk drive.

    • Node 1 (right-most sled) boot drive is the top drive in the chassis. Node 0 (left-most sled) boot drive is the bottom drive in the chassis.

    • Disconnecting the SATA / power cable can be performed on either the motherboard or HDD end of server node 1 . However, the SATA / power cable must be disconnected from the motherboard end on node 0.

  3. Pull the server sled from the chassis.
    • Pull the server sled from the chassis.

  4. Place the server sled on a work surface.
    • Place the server sled on a work surface.

Conclusion